Despite a multi-million
rand modernisation process,
Maydon Wharf (MW) in the
Port of Durban will, for years
to come, remain too shallow for
the bigger ships for which it has
been designed.
Six of the 15 MW berths
– all together comprising
the largest breakbulk and
dry-bulk handling precinct
in the harbour – are having
R1.6 billion spent on them for
reconstruction and deepening.
Transnet National Ports
Authority (TNPA) told FTW:
“Berths 1-2 and 13-14 are
currently under construction
following the reconstruction of
berth 12, which was completed
in November 2012. Berths
3-4 are due to be under
construction early this year.”
But, for some considerable
time, the larger ships able to
use them will have to sail in
only part-loaded. According
to TNPA, the final charted
depth (CD) of the berths will be
14.5m, allowing a maximum
permissible draught of 13m.
But, it added, the MW entrance
channel and berths will still
need to be deepened after the
berth upgrades are complete
to enable these vessels to sail in
fully laden.
And the latest permissible
drafts released by the port
authority on February 3 show
just how little depth is currently
available. MW berths 3 to 7 and
9 are only 9.3m; berths 8, 11
and 12 are 10m; and berth 10 a
miserly 8.5m.
And none of the lines using
MW are happy about the fact
that their larger vessels – up
to 55 000 tonnes deadweight
(DWT) – now calling “are
mostly going to be able to sail
only half-laden due to the
current draught and width
restrictions”, admitted TNPA.
This is a loss of tonnage
greater than the full capacity
of the 20 000-DWT ships that
used to call.
Peter Besnard, CEO of
the SA Association of Ships
Operators and Agents (Saasoa),
told FTW that the deepening
was no quick fix, and would
take an enormous amount of
time to be completed.
And FTW has been told by
other sources that part of this
wait is caused by the same delay
factor that has held up the final
upgrade and deepening of the
Durban Container Terminal
(DCT) berths 203-205. This
was for the project to pass
the environmental impact
assessment (EIA). And the
Green bodies in the city were
up in arms about the fact that
this upgrading project would
eat up another 50m of the
historic harbour sandbank – a
vital breeding ground for lots
of marine animals.
But, considerably later,
this has now been passed,
according to TNPA. The next
step is to extend the DCT pier’s
berths 203-205 by 50m. And
the deepening can only happen
after that is all complete.
The same EIA will come up
for the MW berth and entrance
channel deepening. And FTW
has been told that this has not
yet been started – and that the
Greens are waiting.
And the cost to importers
and exporters? We were told by
one shipper: “You can bet your
bottom dollar that the lines
won’t be absorbing the cost of
ships sailing half empty. They
will, by one means or another,
pass it on to us, the cargo
owners – and eventually to the
end consumers.”
To try to get some idea of the
datelines, FTW asked TNPA:
“What is the timing schedule for
this berth and entrance channel
deepening? In other words,
when are the various dredging
projects due to be finished,
and in what order?” However,
nothing but the sounds of
silence was received before we
were due to go to print.
Concerns raised over Durban berth deepening timelines
12 Feb 2016 - by Alan Peat
0 Comments
FTW - 12 Feb 16

12 Feb 2016
12 Feb 2016
12 Feb 2016
12 Feb 2016
12 Feb 2016
Border Beat
16 Apr 2025
Featured Jobs
New
New